Runway 18/36 Reconstruction Project — $9.9 million

FAA n $6,721,484

HTAC – $2,781,652

State – $457,210

Clendenning Road Drainage — $186,411

HTAC – $93,205

TPCG* – $93,205

*Parish to reimburse half of total cost by 2010, has reimbursed $20,000 to date

Security Lighting n West Ramp South

HTAC – $84,260.36

Re-Striping Runway 12/30 n 5,000 feet

HTAC – $36,000

Security Lighting n Taxiway “G”

HTAC – $318,307

Reconstruction of Portions of Taxiways B, E, and H — $4.4 million

HTAC – $1,305,170

FAA – $2,994,816

State – $157,622

AWOS — $216,327

HTAC – $187,00

State – $60,000

AWOS Access Road and Perimeter Fence

HTAC – $187,000

New HTAC Office Facility

HTAC – $1.2 million

Re-cabling 18/36

State – $305,000